All American Asphalt will be resurfacing E. Grand Avenue between Center St. and Pacific Coast Hwy beginning next Wednesday, October 19, 2022.

The project locations are:

  • E. Grand Ave. between approximately 30 feet west of Center St. and Pacific Coast Hwy, including the intersections except for the Grand Ave./Pacific Coast Hwy intersection

  • Approximately 30 feet north and south of E. Grand Ave. on Center St.

  • Approximately 30 feet north of E. Grand Ave. on Indiana St. and Illinois St.

The tentative construction schedule, from 9 am to 3 pm, is:

  • October 19 – 21: Grinding the existing asphalt pavement, installing new asphalt pavement, and placing temporary traffic striping and markings

  • October 24 – November 4: Installing new traffic loops on eastbound E. Grand Ave. at Pacific Coast Hwy and east and westbound in advance of the E. Grand Ave./Kansas St. Intersection.

  • November 7 – November 11: Re-striping and installation of pavement markers

The schedule may change due to material availability, weather, unforeseen utility conflicts, etc.

Project Contacts:

  • City Public Works Department: Floriza Rivera, (310) 524-2361 and frivera@elsegundo.org

  • Project Inspector: Pedram Abbassi, Wallace & Associates, (714) 486-8096

  • Stephen Doreck Equipment Rentals Superintendent: Rick Hernandez, (310) 892-8766